Project insight

The 7-Step Solar + Storage Procurement Checklist I Wish I'd Had Before Perth

Commercial solar and battery procurement is full of hidden line items. This is the 7-step checklist I use to keep them out of my budget—covering GoodWe spec verification, ESS lithium battery TCO, and solar panel removal and reinstall.

Why This Checklist Exists

I'm the office administrator for a 300-person company. Facilities procurement—cleaning, security, maintenance, capital equipment—runs through me. Solar wasn't a stretch technically. It was a stretch financially.

Last year, our operations team asked me to get quotes for solar plus battery storage at our Perth office. I did what I usually do: request five quotes, compare totals, pick the middle one. That approach cost us $2,400 in a line item nobody flagged until the invoice arrived. It's a lesson I learned the hard way, and I'm not eager to learn it twice.

So here's the checklist I now use. Seven steps, in order, each with a checkpoint. If you're a procurement lead, ops manager, or administrator handling your first commercial solar or ESS project, this is what I'd hand you.

Step 1: Verify Every Component Against the Manufacturer's Spec Sheet

Don't trust the brochure. Not because your installer is dishonest—most aren't—but because brochures get recycled across product generations. I burned a week last spring comparing specs from a PDF that was 18 months out of date.

Our Perth-based installer quoted GoodWe solar inverters—they're common in the Australian mid-market, and stock is usually available locally. Fine. But "GoodWe" covers a dozen models, and the differences between them (grid-tie vs. hybrid, single vs. three-phase, power output) actually matter.

So now I do this:

  • Ask the installer for exact model numbers, not product families. "GoodWe hybrid" isn't a model. GW5000-EH is.
  • Pull the spec sheet from the GoodWe official website, not from the installer's PDF.
  • Check the sheet's date. If it's more than a year old, ask the installer to confirm nothing has been superseded.

Checkpoint: can I match every model number on the quote to a current manufacturer spec sheet? If not, the quote doesn't move forward.

Step 2: Verify the Installer, Not Just the Product

Perth has plenty of solar installers. Not all of them will still be trading when your warranty needs servicing in year seven. That's not pessimism—that's procurement.

I now require three things from any installer:

  • Licence number and current electrical contractor registration.
  • Proof of public liability insurance (minimum $10M is standard for commercial work).
  • Two reference sites from the last 18 months, ideally within an hour of our office.

I call one of the references. I ask two questions: "Did the install run to schedule?" and "Have you had to call them back for anything?" The pause before the second answer tells you more than the answer itself.

Step 3: Compare Total Cost of Ownership, Not the Quote Total

This is the step where most of us get it wrong. I know I did.

It took me three years and roughly 150 procurement orders to understand that the lowest quote and the lowest cost are two different numbers. On our project, a $9,500 quote ended up costing $12,200 once I added the monitoring subscription, the council permit fee the installer forgot to include, the electrical upgrade to the switchboard, and the two days of productivity we lost while the crew was on site longer than planned.

When I look at an ESS lithium battery machine bundled into a solar quote, I break the TCO into five lines:

  1. Equipment and installation (the quote total)
  2. Permits, inspections, and utility connection fees
  3. Monitoring subscription or software costs over five years
  4. Expected maintenance and warranty service visits
  5. Downtime or disruption to our operations during install and first-year service

Checkpoint: can I show my finance director a five-year cost number, not an invoice number? If not, keep asking questions.

Step 4: Budget for Solar Panel Removal and Reinstall If There's Any Roof Work

This is the step almost everyone skips, and it's the one that ate my $2,400.

We were replacing part of the office roof within 18 months of the solar install. The original installer's quote didn't mention that the panels would need to come off and go back on. When we asked later, the number came back at $2,400 for solar panel removal and reinstall alone—not including the roofer's time.

Now I ask directly: "Does our roof have any planned work in the next five years?" If yes, solar panel removal and reinstall goes into the original budget, not the contingency line.

I said "fully turnkey" when I sent the brief. The installer heard "equipment installed, everything else excluded." We were using the same words but meaning different things. Discovered it when the roof quote arrived without panels mentioned.

Checkpoint: is the removal-and-reinstall cost written into the contract, not just discussed verbally?

Step 5: Sanity-Check Output Using a Reference You Actually Understand

I'm not an engineer. I don't need to be. But I do need a rough sense of whether the system the installer is proposing produces a number that makes sense for our usage.

Here's my trick: I ask how many homes a wind turbine power, and use that as a benchmark. A typical 2 MW commercial wind turbine powers roughly 500–600 homes, depending on capacity factor and average household consumption. Our office uses about as much electricity as 12 homes. So when an installer proposes a system sized for 200 homes, I know to ask whether we're actually generating excess power or whether there's a mismatch somewhere.

That's not a technical calculation. It's a sanity check. It tells me whether I need to bring in a consultant. Most of the time, I don't. But once, I did.

Step 6: Confirm Warranty, Monitoring, and After-Sales Support in Writing

Per FTC advertising guidelines (ftc.gov), warranty and performance claims in sales materials must be truthful, not misleading, and substantiated with evidence. That's useful leverage when you're reviewing quotes—it means "12-year warranty" on a brochure means nothing unless someone can point to the terms behind it.

I require three things in writing:

  • Equipment warranty terms, including who honours them (manufacturer, installer, or both).
  • Monitoring platform—what's included, what's an add-on, and what happens to our data if we change installers.
  • Response time commitments for service calls. "Within 24 hours" needs to be in the contract, not in the sales call.

Checkpoint: if I have to escalate a warranty claim, whose phone do I call first? If the answer consists of vague names, add that to the risk column.

Step 7: Tie Final Payment to Acceptance, Not to the Calendar

The installer will want staged payments. That's fine. What I don't do anymore is release the final 10–20% on a date. I release it on acceptance.

Acceptance means: system is live, monitoring dashboard is functioning, all permits are closed out, and I've received the as-built documentation. No exceptions.

This saves a ton of back-and-forth later. The upside of paying early is a mildly happier installer. The risk is discovering a problem after the money's gone. I've learned which side of that trade-off I prefer.

Checkpoint: is the final payment condition clearly written, with a defined acceptance checklist, and no "unless otherwise agreed" escape hatch?

Common Mistakes to Avoid

Three mistakes I've made, so you don't have to:

  • Confusing "no deposit" with "no risk." A vendor that doesn't ask for a deposit often means they need the cash flow. That's not automatically a red flag, but it's worth asking about.
  • Skipping the reference call because the price was good. Price and install quality are only loosely correlated. I learned that on a different project (circa 2022) and I still remember it.
  • Assuming "standard install" means the same thing to everyone. It doesn't. Ask what's excluded. Write it down. Sign it.

None of this makes me an expert on solar technology. It makes me a procurement person who's lost money once and isn't planning to do it again. The seven steps above are boring, and that's the point. Boring is what keeps the $2,400 refundable.